Location: Bullaven Farm, near Ivybridge, Devon
Client: Woodland Trust
Funding: Plymouth and South Devon Community Forest
Services: Tree planting, woodland pasture planting, woodland infill, orchard planting, hedgerow shelterbelt planting, stock fencing, tree protection installation
Project length: Completed within the 2025 planting season

Client Brief

Bullaven Farm is a beautiful moorland farm sitting between Dartmoor and the town of Ivybridge. It is rugged, exposed and steep in places, with the sort of ground that looks impressive from a distance but becomes much harder work once you are actually carrying materials across it in winter.

We were contacted by the Woodland Trust in mid-January, very late in the planting season, to help deliver a Community Forest funded scheme before the end of March. The project had come to us through recommendation, following previous work we had carried out at Duchy College.

The timescale was tight from the start. This was not a small block of straightforward planting. The scheme included woodland infill, low-density wood pasture, hedgerow shelterbelt planting, orchard planting and fencing. Each part of the project had a different purpose, planting density and protection method, so it needed careful organisation on the ground.

Our role was to provide the planting labour and practical expertise to get the work delivered properly, on time and within the planting window.

THRC Solution

A Mixed Planting Scheme Across the Farm

The planting was split into four main areas.

The woodland infill involved planting 1,200 native trees into existing woodland areas. This type of planting is about strengthening what is already there, filling gaps, improving future canopy structure and helping the woodland become more varied over time.

The low-density wood pasture covered a much wider area, with 405 trees planted using cactus guards. This was a very different style of planting. Rather than creating closed woodland, the aim was to establish individual trees across grazed or open ground, allowing the farm to keep its open moorland character while adding long-term parkland-style tree cover, shelter and habitat value.

The largest element was the hedgerow buffer and shelterbelt planting, with 3,842 plants installed. This part of the scheme will help create stronger habitat corridors across the farm, giving birds, bats, insects and small mammals better cover and movement routes. It should also provide shelter in some of the more exposed parts of the site, which is important on a farm sitting so close to the edge of Dartmoor.

The orchard was smaller in scale, but still an important part of the scheme. We planted 18 orchard trees and installed individual chestnut post and rail guards around each one. The orchard brings a different kind of value to the farm, with flowering and fruiting trees that will benefit pollinators, birds and the wider landscape as they mature.

Species across the scheme included oak, sessile oak, alder, aspen, crab apple, hawthorn, hazel, rowan, field maple, dog rose, dogwood, guelder rose, spindle, small-leaved lime and others. The orchard included a mix of fruit and nut trees.

Access, Weather and Logistics

The biggest challenge on this job was access.

The farm is steep, rocky and exposed, with rough moorland ground and difficult weather. We had strong wind, heavy rain, underlying granite, encroaching vegetation and a serious amount of ticks to contend with throughout the project.

We used our ATV Gator to move people, trees, stakes, tubes, guards, mulch mats, tools and fencing materials from a base barn at the bottom of the farm up to the different planting areas. Without it, the job would have taken far longer and put a lot more strain on the team.

The materials had also been delivered to a neighbouring site before we arrived, which created an immediate logistical problem. That was outside our scope and not caused by us, but it still had to be worked around. With help from the Woodland Trust, the issue was resolved and the materials were brought back to the correct place so the project could keep moving.

That was the theme of the job in many ways. There were several details that had either been missed or changed late on, and we had to keep solving them without letting the programme slip.

Tree Protection and Planting Detail

Most of the trees were planted with 1.2m tubes, stakes and mulch mats because of the high deer pressure on and around the farm.

The low-density wood pasture trees were planted with cactus guards, which suited the purpose of that part of the scheme. These trees were more exposed and more widely spaced, so the protection needed to give them a better chance of establishing in open ground.

The planting itself was fairly straightforward in principle, but hard in practice. Every part of the site felt different. Some areas had thick vegetation, some had shallow soils over granite, some were more exposed to the weather, and some needed careful attention to the different planting densities shown on the plan.

It was important not to treat the whole farm as one planting block. The woodland infill, wood pasture, shelterbelt and orchard all had different reasons for being there, so they had to be planted accordingly.

Fencing and Orchard Guards

Alongside the planting, we installed 125 metres of stock fencing with two strands of barbed wire.

This was carried out in the same field as the orchard, where the ground proved particularly difficult. A river of granite ran through the field, which made driving posts hard going. We hired in a tracked post banger for the fencing and orchard guard works, which gave us the best chance of getting the posts in properly without losing too much time.

Each of the 18 orchard trees was protected with its own chestnut post and rail guard. These guards were built to give the fruit and nut trees proper protection while still looking appropriate in the setting.

End Result

Delivering Before the Season Closed

The main pressure on this project was time.

We were brought in late, the site was difficult, the weather was poor, and the scheme had several moving parts. Despite that, the planting and fencing were completed before the end of the season, within budget, and to the satisfaction of the Woodland Trust, the landowner and the project funders.

For us, Bullaven Farm was a good example of the kind of project where organisation matters just as much as the physical work. Anyone can look at a planting plan and count trees. The harder part is getting the right people, kit and materials to the right places, dealing with the problems that appear on site, and still finishing the job properly before the planting window closes.

The finished scheme gives the farm a much stronger network of trees, shelterbelts, orchard planting and future wood pasture. Over time, it should add shelter, improve habitat connectivity, increase species diversity and help the farm develop a more varied and resilient landscape.

Services Included

  • Tree planting
  • Woodland infill planting
  • Low-density wood pasture planting
  • Hedgerow buffer planting
  • Shelterbelt planting
  • Orchard planting
  • Native species planting
  • Tree protection installation
  • Cactus guard installation
  • Mulch mat installation
  • Chestnut post and rail orchard guards
  • Stock fencing
  • Barbed wire fencing
  • Tracked post banger fencing works
  • ATV-assisted site logistics
  • Community Forest scheme delivery
  • Woodland Trust project delivery