Location: Duchy College, Cornwall
Client: Duchy College
Project partners: Woodland Trust
Services: Agroforestry planting, silvopasture planting, farm tree planting, browsable hedge planting, standard tree planting, annual maintenance
Project length: 1 week

Client Brief

Duchy College contracted us to help deliver an agroforestry planting scheme on their Future Farm Project.

The Future Farm is focused on improving efficiency, technology and welfare in dairy farming, so this planting scheme had to work as part of a real agricultural system. It was not just about putting trees into a field because they looked good. The planting needed to support how the farm would be managed, how the herd would move, and how the field would function over time.

The scheme was based in Smiths Field and followed a planting plan provided by the Woodland Trust, who were also involved in supporting and funding the project. The aim was to create future grazing paddocks for the college’s 200-cow dairy herd, while improving soil health, adding shelter and shade, and creating browsable foliage along the outside rows.

This project also had a demonstration and trial value. As part of Duchy College’s wider Future Farm work, the planting needed to show how trees can be integrated into a productive dairy system without taking the field out of use.

This was our first agroforestry project for Duchy College, and it later led to further riparian planting work on the campus.

THRC Solution

Planting for a Working Dairy System

The design included three main rows of trees, with each row made up of three planting lines.

The outside lines were planted as coppiceable browse rows and wind shelters. Species included goat willow, hazel, rowan and aspen. These were chosen to provide a more immediate low-level structure, with foliage that could eventually offer browsing value and shelter along the grazing paddocks.

The middle line was planted with standard tree species intended to provide longer-term shelter, shade and potential timber value. Species included English oak, field maple, walnut, wild cherry and silver birch.

That mix gave the planting several jobs to do at once. The outer rows should establish as lower, denser shelter and browse lines, while the central standard trees should form the long-term structure of the agroforestry system.

Following the Planting Plan

We worked from the supplied plans and maps, liaising with the Future Farm Manager and project lead at Duchy College throughout the job.

Between 1,000 and 1,500 trees and shrubs were planted. The stock and guards were supplied through Duchy College and the Woodland Trust, with our role focused on accurate implementation of the design.

The standard trees were planted first at 10m spacings through the central rows. These were protected with 1.6m plastic-free tree guards and supporting stakes, giving the scheme its main framework.

Once the central rows were in place, we planted the browsable hedgelines alongside them at 1m spacings. These were installed with 60cm tube guards and stake supports.

The spacing mattered. This was not a general shelterbelt where small variations would make little difference. It was a structured agroforestry layout designed to divide future paddocks and work alongside a grazing regime, so the rows, gaps and species positions all needed to be right.

Working Around Farm Constraints

Like most farm planting projects, the work had to fit around the realities of the site.

We had to negotiate water troughs, gas lines, steep contours and the need to keep long planting lines straight across uneven ground. Those sorts of constraints can look minor on paper, but they affect where trees can safely go and how the finished scheme will work.

The fencing was installed after the planting, so the trees had to be protected properly from the start and the layout had to remain clear for the fencing contractors to follow.

Good agroforestry planting needs that balance. The trees have to be planted accurately, but they also have to sit sensibly within the farm infrastructure.

End Result

The Result

The planting was completed efficiently and accurately, with the correct species placed in the correct rows and the required spacings followed throughout.

Duchy College now has a new agroforestry layout within Smiths Field, helping divide future grazing paddocks while adding shade, shelter, browse, soil benefits and biodiversity value to the dairy system.

For the herd, the planting should eventually provide more shelter and shade across the field. For the farm, it adds structure and long-term resilience. For wildlife, the mix of native and productive tree species should provide blossom, foliage, insects, nesting opportunities and better habitat connectivity across the farm.

For THRC, this was a useful project because it showed we could deliver tree planting within a working agricultural system, where the details of spacing, species, protection and farm infrastructure all mattered.

It also showed that we can follow a supplied agroforestry design properly, while still making practical decisions on the ground.

Annual Maintenance

We are continuing to maintain the scheme annually.

That follow-up work is important. Agroforestry planting has to establish successfully before it can provide the shelter, shade, browse and habitat value it was designed for. Annual maintenance gives the planting a much better chance of becoming part of the working farm system rather than simply being a one-off planting exercise.

Services Included

  • Agroforestry planting
  • Silvopasture planting
  • Farm tree planting
  • Dairy farm tree planting
  • Browsable hedge planting
  • Coppice row planting
  • Standard tree planting
  • Shelterbelt planting
  • Shade and shelter planting
  • Plastic-free tree guard installation
  • 1.6m tree guard installation
  • 60cm tube guard installation
  • Stake installation
  • Planting to supplied Woodland Trust design
  • Working around farm infrastructure
  • Gas line awareness
  • Water trough constraint working
  • Steep contour planting
  • Future paddock planting
  • Agroforestry trial and demonstration support
  • Annual maintenance
  • Duchy College project delivery
  • Future Farm planting support